163. The authorization holder must submit to the Minister, for approval, the corrective actions to be taken where any of the following situations occurs:
(1)  a cementing operation provided for in the technical program cannot be carried out;
(2)  no cement return is observed on the surface where such return was planned;
(3)  a return of drilling fluid indicates that the cement height required for cementing is not reached;
(4)  there is uncertainty as to reaching the cementing goals.
O.C. 1252-2018, s. 163.
In force: 2018-09-20
163. The authorization holder must submit to the Minister, for approval, the corrective actions to be taken where any of the following situations occurs:
(1)  a cementing operation provided for in the technical program cannot be carried out;
(2)  no cement return is observed on the surface where such return was planned;
(3)  a return of drilling fluid indicates that the cement height required for cementing is not reached;
(4)  there is uncertainty as to reaching the cementing goals.
O.C. 1252-2018, s. 163.